D-STOR: a battery park with the right balance
16 October 2026D-STOR: a battery park with the right balance
16 October 2026
Civil works and a high- and medium-voltage substation for a 140 MWh battery park
How do you prepare a large-scale battery park for connection to the high-voltage grid? For the new D-STOR battery park in La Louvière, jointly owned in equal shares by BSTOR and Duferco Wallonie, Equans Belux delivered the Balance of Plant civil works and installed a high- and medium-voltage substation. With a power rating of 50 MW and a storage capacity of 140 MWh, the project supports the flexibility of the Belgian electricity grid. Equans brings its expertise in civil engineering and high- and medium-voltage infrastructure to the project.
Managing the complexity of a battery park
The D-STOR project required close coordination between the various partners and their respective scopes of work. The challenge for the client and its partners was to integrate 36 Tesla Megapacks with a 150 kV grid connection, high-, medium- and low-voltage installations, civil works, safety systems, fibre optics and SCADA, while bringing the existing line back into service. The schedule also had to accommodate long equipment lead times and the requirements of multiple stakeholders, including Elia, ORES, Tesla and Duferco Wallonie, the project partner and site owner.
Equans delivers the civil works and high- and medium-voltage substation
Equans’ scope covers two clearly defined areas: the Balance of Plant civil works and the installation of a high- and medium-voltage substation. Following the signing of a preliminary agreement (LNTP) in late 2023, Equans began critical engineering studies and placed equipment orders within its scope to mitigate schedule risks. Its teams oversee technical delivery, safety and the execution of their works, in coordination with the other parties involved.
From complex interfaces to reliable energy storage
The project’s infrastructure was energised in February 2026. With a power rating of 50 MW and a storage capacity of 140 MWh, D-STOR enables large-scale energy storage to support the flexibility of the Belgian electricity grid. By delivering the Balance of Plant civil works and installing the high- and medium-voltage substation, Equans contributes to the infrastructure needed for this storage capacity and its grid connection, alongside the other project partners.
Frequently asked questions about battery storage systems (BESS)
Do you have any questions about our battery storage systems and related services? We're here to make everything clear and easy to understand.
Can’t find the answer you’re looking for?
D-STOR is a front-of-the-meter energy storage project designed to support electricity grid flexibility. Located in La Louvière, the battery park has a power rating of 50 MW and a storage capacity of 140 MWh.
The project combines 36 Tesla Megapacks with a 150 kV grid connection and requires coordination across civil works, electrical installations, and control and safety systems. The challenge is to manage the interfaces between these work packages while taking account of stakeholder requirements and equipment lead times.
Equans delivered the Balance of Plant civil works and installed a high- and medium-voltage substation. These two areas form part of a project delivered by several partners, each with clearly defined responsibilities.
By combining its expertise in civil engineering and high- and medium-voltage infrastructure, Equans helps prepare the battery park for its grid connection. Its teams bring together engineering studies, safety oversight and the execution of works within their scope, with a particular focus on interface management.
Following the signing of a preliminary agreement (LNTP) in late 2023, Equans began critical engineering studies and placed equipment orders within its scope. This proactive approach aimed to mitigate the risks associated with long lead times, alongside ongoing coordination with the other parties involved in the project.
The civil works, the high- and medium-voltage substation, the batteries and the electrical Balance of Plant for the battery energy storage system (BESS) fall within separate but interdependent scopes. Clearly defined responsibilities and close coordination at the interfaces are essential to technical consistency, safe execution and smooth project delivery.
With a power rating of 50 MW and a storage capacity of 140 MWh, D-STOR provides large-scale energy storage to support grid flexibility. Its front-of-the-meter purpose sets it apart from an installation designed for on-site self-consumption or peak shaving.